Steel Fabrication

Weymouth STW – Inlet Steelwork 

Critical H&S Access and Structural Improvement 

Scope:

Weymouth STW - A statement of need came from a pell frischmann report assessing the H2S attack on the existing steelwork. As a result, Gel Engineering worked with Wessex Water to replace the main steelwork around the inlet screens and action repairs on faults which have been reported as a level 4/5 H&S risk.  

Gel employed as Principal Contractor responsible to produce all relevant paperwork including RAMS, CPP, H&S File and Programme of Works, with sufficient time for amendment/review (10 days minimum). 

  • Provision of all required plant to conduct the full scope of works. 

  • Requirement to plan, manage & monitor the scheme throughout the duration of the works, as per CDM requirements. 

  • Remove all existing steelwork and platforms for screens 1-4.  

  • Installation of flooring, handrailing and overflow pipework to Wessex Water standards. 

Electrical contractor to move isolators on band screens and replace the tray work. 

  • Hire of equipment required for the project. 

  • Skips for waste removal. 

  • Supply and install of like for like stainless steel pipe bridge to replace corroded existing galvanised unistrut bridge. 

  • Supply and install new flooring by cutting out existing concrete and rebating new flooring structure and OMF. 

  • Supply and install new like for like grit detritor access bridge.